AP ICET 24 May 2023 Shift 2 Solved Paper

© examsiri.com
Question : 168 of 200
 
Marks: +1, -0
P, Q and R can complete a work separately in 16,32 and 48 days respectively. They started work together. But Q leaving off 8 days and R,6 days before the completion of the work. In what time is the work finished?
Go to Question: