You are a Project Manager for your organization. Your project has a BAC of $250,000 and is expected to last ten months. Currently the project is in month six and is 40 percent complete, but the project was expected to be sixty percent complete by this time. You have spent $125,000 to complete the work. What is the Cost Performance Index of the project?