CAPM Certification Practice Test 2
© examsiri.com
Question : 9 of 50
Marks:
+1,
-0
Christina, the CIO, wants to know why you have requested so many meetings with the users of the software your project is creating. While she acknowledges that the users are stakeholders she doesn’t understand why you believe these stakeholders should be involved so much during the initiation phase of the project. Why should the stakeholders be involved now?