You are the project manager of a construction project for a new client. The client has asked that you include an outdoor deck as part of the project – something your company doesn’t normally do, but you agree to take on this project component using a contractor to build the seating deck. For this portion of the project you would like to use a time and materials contract. What must this contract type have?