CAPM Certification Practice Test 8
© examsiri.com
Question : 10 of 50
Marks:
+1,
-0
An activity has an Early start(ES) of day 5, a Late Start (LS) of day 15, an Early Finish (EF) of day 8 and Late Finish(LF) of day 18. This activity :