Question : 60 of 66
 
Marks: +1, -0
The amount of job that Amal, Sunil and Kamal can individually do in a day, are in harmonic progression.Kamal takes twice as much time as Amal to do the same amount of job. If Amal and Sunil work for 4 daysand 9 days, respectively, Kamal needs to work for 16 days to finish the remaining job. Then the number ofdays Sunil will take to finish the job working alone, is