DRDO Multi tasking staff Model paper 5
© examsiri.com
Question : 79 of 100
Marks:
+1,
-0
3 men and 5 women can complete a work in 8 days, while 2 men and 6 women can complete it in 10 days. In how many days 10 women will complete it?