In a wastewater treatment plant, primary sedimentation tank (PST) designed at an overflow rate of 32.5 m3/day/m2 is 32.5 m long , 8.0 m wide and liquid depth of 2.25 m. If the length of the weir is 75 m, the weir loading rate (in m3/day/m) is ______________.