The activity details of a project are given below:
The estimated minimum time (in days) for the completion of the project will be_______
|
Activity |
Depends on |
Duration (in days) |
|
P Q R S T U V |
- P Q, T R P Q, T U |
6 15 12 16 10 14 16 |
The estimated minimum time (in days) for the completion of the project will be_______