Question : 40 of 65
Marks:
+1,
-0
Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is
|
Ration of Y’s bid Price of X’s cost |
Number of bids |
|
1.02 |
6 |
|
1.04 |
12 |
|
1.06 |
3 |
|
1.10 |
6 |
|
1.12 |
3 |
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is