GATE Civil Engineering (CE) 2021 Shift 1 Solved Paper

© examsiri.com
Question : 40 of 65
 
Marks: +1, -0
Contractor X is developing his bidding strategy against Contractor Y. The ratio of Y's bid price to X's cost for the 30 previous bids in which Contractor X has competed against Contractor Y is given in the Table
Ration of Y’s bid Price of X’s cost
Number of bids
1.02
6
1.04
12
1.06
3
1.10
6
1.12
3
 
Based on the bidding behaviour of the Contractor Y, the probability of winning against Contractor Y at a mark up of 8% for the next project is