Question : 53 of 65
Marks:
+1,
-0
A small project has 12 activities - N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the Table.
The total float of the activity "V" (in weeks, in integer) is ______.
|
Activity |
Duration (in weeks) |
Depends upon |
|
N |
2 |
- |
|
P |
5 |
N |
|
Q |
3 |
N |
|
R |
4 |
P |
|
S |
5 |
Q |
|
T |
8 |
R |
|
U |
7 |
R, S |
|
V |
2 |
U |
|
W |
3 |
U |
|
X |
5 |
T, V |
|
Y |
1 |
W |
|
Z |
3 |
X, Y |
The total float of the activity "V" (in weeks, in integer) is ______.
- Your Answer:
Go to Question: