The activity details for a small project are given in the Table.
The total time (in days, in integer) for project completion is ______
|
Activity |
Duration (days) |
Depends on |
|
A |
6 |
- |
|
B |
10 |
A |
|
C |
14 |
A |
|
D |
8 |
B |
|
E |
12 |
C |
|
F |
8 |
C |
|
G |
16 |
D, E |
|
H |
8 |
F, G |
|
K |
2 |
B |
|
L |
5 |
G, K |