Question : 61 of 65
Marks:
+1,
-0
An activated sludge process (ASP) is designed for secondary treatment of 7500 m3/day of municipal wastewater. After primary clarifier, the ultimate BOD of the influent, which enters into ASP reactor is 200 mg/L. Treated effluent after secondary clarifier is required to have an ultimate BOD of 20 mg/L. Mix liquor volatile suspended solids (MLVSS) concentration in the reactor and the underflow is maintained as 3000 mg/L and 12000 mg/L, respectively. The hydraulic retention time and mean cell residence time are 0.2 day and 10 days, respectively. A representative flow diagram of the ASP is shown below.
The underflow volume (in m3/day, round off to one decimal place) of sludge wastage is ______
The underflow volume (in m3/day, round off to one decimal place) of sludge wastage is ______