GATE Civil Engineering (CE) 2022 Shift 1 Solved Paper
© examsiri.com
Question : 39 of 65
Marks:
+1,
-0
The project activities are given in the following table along with the duration and dependency.
Which one of the following combinations is correct?
| Activities |
Duration (days) |
Depends on |
| P | 10 | - |
| Q | 12 | - |
| R | 5 | P |
| S | 10 | Q |
| T | 10 | P, Q |
Which one of the following combinations is correct?