Question : 39 of 65
 
Marks: +1, -0
The project activities are given in the following table along with the duration and dependency.
Activities Duration
(days)
Depends on
P 10 -
Q 12 -
R 5 P
S 10 Q
T 10 P, Q

Which one of the following combinations is correct? 