A project has four activities P, Q, R and S as shown below.
Activity
Normal duration (days)
Predecessor
Cost slope (Rs./day)
P
3
-
500
Q
7
P
100
R
4
P
400
S
5
R
200

The normal cost of the project is Rs. 10,000/- and the overhead cost is Rs. 200/- per day. If the project duration has to be crashed down to 9 days, the total cost (in Rupees) of the project is _______