GATE Mechanical Engineering (ME) 2015 Shift 2 Solved Paper

© examsiri.com
Question : 64 of 65
 
Marks: +1, -0
A project consists of 7 activities. The network along with the time durations (in days) for various activities is shown in the figure.

The minimum time (in days) for completion of the project is _____
  • Your Answer:
Go to Question: