Following data refers to the jobs (P, Q, R, and S) which have arrived at a machine for scheduling. The shortest possible average flow time is ________days.
|
Job |
Processing Time (days) |
|
P |
15 |
|
Q |
9 |
|
R |
22 |
|
S |
12 |