GATE Mechanical Engineering (ME) 2022 Shift 1 Solved Paper
© examsiri.com
Question : 58 of 65
Marks:
+1,
-0
An assignment problem is solved to minimize the total processing time of four jobs (1, 2, 3 and 4) on four different machines such that each job is processed exactly by one machine and each machine processes exactly one job. The minimum total processing time is found to be 500 minutes. Due to a change in design, the processing time of Job 4 on each machine has increased by 20 minutes. The revised minimum total processing time will be ________ minutes (in integer).
- Your Answer:
Go to Question: