Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.
Part
Milling (hours)
Polishing (hours)
P1
8
6
P2
3
2
P3
3
4
P4
4
6
P5
5
7
P6
6
4
P7
2
1