Question : 91 of 100
 
Marks: +1, -0
Study the following information carefully and answer the question given below :
A road construction project has been going on in State Y and was due to be completed two months ago. The government of that time had extended the deadline of the project by three months and also allowed truck carrying the raw material to pass through City Z in order to speed up the process. Yet the construction work is further delayed and is not likely to get over in the extended deadline as well. Which of the following may NOT be a reason for the delay of construction work in State Y?