Question : 90 of 200
Marks:
+1,
-0
Efficiency of Asha is 25% more than Usha and Usha takes 25 days to complete a piece of work. Asha started the work alone and then Usha joined her 5 days before actual completion of the work. For how many days Asha worked alone ?