Question : 45 of 70
Marks:
+1,
-0
A project manager is working on a multiphase networking project. Phase 1 is scheduled to finish next month. Phase 2 is in the initiation phase and the budget approval is past due. However, the project manager has a strategy in place for approval.
What should the project manager use to monitor this and help ensure a delay does not impact project performance?
What should the project manager use to monitor this and help ensure a delay does not impact project performance?