PMP Certification Monitoring and Controlling Test 1

© examsiri.com
Question : 58 of 70
 
Marks: +1, -0
A project that uses several vendors is estimated to complete in two years. At the end of the first year, a significant budget overrun is identified. Conscious that the project must be brought back under control, the project manager issues a change request.
What should the project manager do to support the change request?