PMP Certification Practice Test 1
© examsiri.com
Question : 59 of 72
Marks:
+1,
-0
While working on your project, you identify a new risk at 50 percent project completion. There is a very high probability the risk will occur on the project, while at the same time, it is expected to have a low impact. Which of the following mitigation strategies would you use ?
Go to Question: