PMP Certification Practice Test 10

© examsiri.com
Question : 3 of 70
 
Marks: +1, -0
You are a Project Manager for your organization. Your project has a BAC of $400,000 and is expected to last one year. The project work is scheduled to be completed in equal amounts each month. Currently the project is in month three but is only 20 percent complete. You have spent $35,000 to complete the work. What is the planned value for this project?
Go to Question: