Question : 8 of 70
Marks:
+1,
-0
Your organization completes projects for other organizations. You are the project manager of the BGV Project. It is almost complete but the stakeholders have requested a change to the project scope. The customer is willing to pay any additional fees for this change. This additional change will cause the project to run three weeks longer than was planned. The problem, you realize, is that you have already scheduled your current project team to start a three-year project for a different customer that will overlap with the new work the customer has just added to the scope. You need to complete the current project, keep your current customer happy, and start the next project on time. What should you do?