PMP Certification Practice Test 5

© examsiri.com
Question : 16 of 72
 
Marks: +1, -0
You are the project manager for your organization and you’ve identified several mistakes in the project deliverables. You’d like to investigate the issue more closely and your project sponsor recommends you create an Ishikawa diagram. What is an Ishikawa diagram?