Question : 11 of 72
 
Marks: +1, -0
You are a Project Manager in the early phase of estimating the cost of the project. You use the analogous method of estimating and have come up with the rough order of magnitude. While presenting it to your sponsor and stakeholders, one of the stakeholders asks if you have also done lifecycle costing for the project. What is your BEST response?