PMP Certification Practice Test 9
© examsiri.com
Question : 10 of 72
Marks:
+1,
-0
As a newly assigned project manager on a large scale international project, Kate has recently developed the risk responses to handle the high ranking risks from the prioritized list of risks. Kate is preparing to proceed to the control risks process when Dave ( A colleague and fellow project manager from another project) reminds her of an important task she left out in the Plan Risk Response Process. What did Dave tell her ?
Go to Question: