A Belt working in a supply chain environment has to make a decision to change suppliers of critical raw materials for a new product upgrade. The purchasing manager is depending on the Belt’s effort requiring that the average cost of an internal critical raw material component be less than or equal to 3,600 in order to stay within budget. Using a sample of 42 first article components, a Mean of the new product upgrade price of 3,200 and a Standard Deviation of 180 wasestimated. Based on the data provided, the Z value for the data assuming a Normal Distribution is?