Question : 64 of 100
Marks:
+1,
-0
The ratio of the efficiencies of A, B and C, to do a certain work is 7 : 3 : 5. Working together, they can complete the work in 21 days. A and C worked together for 15 days. The remaining work will be completed by B alone in: