Time and Work Practice Test 2 with solutions

© examsiri.com
Question : 34 of 40
 
Marks: +1, -0
A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3 days before the completion of the work, A leaves off. The total number of days to complete the work is—
Go to Question: