Processing times (including step times) and due dates for six jobs waiting to be processed at a work centre are given in the table. The average tardiness (in days) using shortest processing time rule is (correct to two decimal places).
JobProcessing time (days)Due date(days)
A38
B716
C44
D918
E517
F1319