PMP Certification Practice Test 2
© examsiri.com
Question : 1 of 72
Marks:
+1,
-0
A project activity has the following values for the earliest and latest it can start and the earliest and latest it can be completed. An activity's Late Start (LS) is 5/day and Late Finish is (LF) 10/day. Similarly Early Start (ES) is 3/day and Early finish (EF) is 8/day. What is the float of this activity?
Go to Question: