You are assigned as a Project Manager to a project in the execution stage. Current schedule and performance indices for the project, SPI and CPI are 1.12 and 1.15, and project performance are well within the baseline. The defects found during internal testing for the last deliverable were well below the organization limits. However, the customer doesn't seem to be happy with the project progress. What should be the FIRST thing the Project Manager should do?